Planned Maintenance CH-008909 - 3BEN and 3SHP NBN POI(s)
Scheduled Maintenance Report for FSG
Completed
The scheduled maintenance has been completed.
Posted Oct 09, 2024 - 08:00 AEDT
In progress
Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Oct 09, 2024 - 01:00 AEDT
Scheduled
Change ID: CH-008909

Maintenance Window:
======================
Start Date & Time: 09/10/2024 00:00:00 AEDT
Finish Date & Time: 09/10/2024 07:00:00 AEDT

Impact
======================
Service Impact: Up to 7 hour service interruption within a 7 hour maintenance window.

Summary
======================
FSG engineers have been notified by our backhaul provider that they need to perform maintenance on the equipment servicing the following NBN POI(s).:
- 3BEN (Bendigo)
- 3SHP (Shepparton)


During the maintenance window customers will experience a service interruption to the impacted POI(s) after which service will restore.

Our NOC will monitor this work closely and send an additional advisory should the maintenance be unsuccessful or have to be rolled back.


Kind Regards,

FSG NOC
E: support@fieldsolutions-group.com
W: www.fieldsolutions-group.com
Posted Sep 23, 2024 - 11:47 AEST
This scheduled maintenance affected: VIC NBN POIs (Backhaul - NBN POI, NBN POI - 3BEN (Bendigo), NBN POI - 3SHP (Shepparton)).