Notification of Routine Maintenance NTF000029084 - NEXTDC P1 DC and 6APP; 6CAN; 6DBL; 6GLT; 6HIL; 6KEL; 6PEA; 6PNJ NBN POI(s)
Scheduled Maintenance Report for FSG
Completed
The scheduled maintenance has been completed.
Posted Jul 17, 2024 - 08:00 AEST
In progress
Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Jul 17, 2024 - 04:00 AEST
Scheduled
Notification ID: NTF000029084

Notification of Routine Maintenance
Start Time: 17/07/2024 04:00:00 (AEST) - 02:00:00 (AWST)
End Time: 17/07/2024 08:00:00 (AEST) - 06:00:00 (AWST)

Purpose of Maintenance:
FSG will be performing software upgrades to our networking equipment hardware located in our NEXTDC P1 (NXTP1) POP during the maintenance window.
This undertaking is part of FSG's ongoing routine maintenance work to implement vendor recommended software updates of our networking infrastructure. These updates ensure the security and reliability of the service we deliver to our Customers.
FSG always indicates a longer maintenance window than required, so that in the rare event of any issues, our engineers can resolve them within the prescribed maintenance window.

Affected Services:
- Connectivity to NBN POIs 6APP; 6CAN; 6DBL; 6GLT; 6HIL; 6KEL; 6PEA; 6PNJ
- This will affect associated NBN services including:
- Connectivity Virtual Circuits (CVC) and attached Access Virtual Circuits (AVC)
- Virtual NNIs (VNNI)
- Enterprise Ethernet (EE)
- Customer NNI services connected at NEXTDC P1 (NXTP1)

Expected Impact:
Customers will experience 2 outages of up to 15 minutes each as the maintenance work is being undertaken.
The total time the network will be in a hazardous state is estimated to be no more than 5 hours.

Our NOC will monitor this work closely and send an additional advisory should the maintenance be unsuccessful or have to be rolled back.
Thank you for your patience while we make these critical improvements, if you have any questions related to this issue please don't hesitate to respond to this email.

Kind Regards,

FSG NOC
E: support@fieldsolutions-group.com
W: www.fieldsolutions-group.com
Posted Jul 04, 2024 - 14:36 AEST
This scheduled maintenance affected: WA Core Network and Data Centres (Infrastructure - NEXTDC P1) and WA NBN POIs (NBN POI - 6APP (Applecross), NBN POI - 6CAN (Cannington), NBN POI - 6DBL (Doubleview), NBN POI - 6GLT (Geraldton), NBN POI - 6HIL (Hilton), NBN POI - 6KEL (Kelmscott), NBN POI - 6PEA (Wangara Depot), NBN POI - 6PNJ (Pinjarra)).